Dispute Resolution Case Studies
BESPOKE CONTRACT
Independently review the delay to the planned completion date by a Major Civil Engineering Contractor.
Sector
Construction
Client
Balfour Beatty
Project
RAF Marham. £90m
Product
Extension of Time Submission & Quantum
Sector
Construction
Client
Balfour Beatty
Project
RAF Marham. £90m
Product
Extension of Time Submission & Quantum
WHY CHOOSE US
Collins has established a growing capability in this sector of work. Our management and delivery skills have been in demand to support this most dynamic and specialist industry.
BACKGROUND
Delay and disruption submission providing a high level evaluation of the time and cost entitlement on three sites within the base and assessment of preliminary costs to manage the whole project.
BRIEF
The brief is for Collins Project Delivery Limited (Collins) to carry out programme delay impact analysis and prepare delay and disruption narrative to support and reinforce findings.
RESULTS
TBA